How to turn a rental unit in three days

Vacancy is rarely lost to the work itself — it is lost between the trades. A turnover finishes quickly when the sequence is fixed before the first crew arrives.

Last updated:

Before day one

Confirm the unit is fully empty, access is on a lockbox or smart lock, and utilities are on in the owner's name. Each of these missing costs a full day.

Approve the work list from the move-out inspection in writing. Approvals that arrive mid-job stop the crew.

Day one: clear and repair

Anything left behind is removed first, then repairs and drywall patching run the same day so patches can cure before paint.

Day two: paint

Walls, trim and ceilings where needed. Painting before cleaning is not optional — reversing the order means paying for the clean twice.

Day three: clean, inspect, photograph

Full empty-unit clean, detector and lock verification, then the dated photo set that documents the condition you are handing to the next tenant.

Why the sequence matters

Every trade that works in the wrong order creates rework. Painting before repairs means patching fresh paint. Cleaning before painting puts dust on wet walls. Removing left-behind items last means the painter works around boxes. A fixed sequence — clear, repair, paint, clean, inspect — avoids each of these.

Where turnovers lose days

Most delays come from access and parts, not labour. Keys that are not handed over on time, a building that needs a certificate of insurance before a vendor can enter, an elevator that must be reserved, or a replacement part that must be ordered can each stop work for a day. Collect these before the move-out date.

The second source is scope creep: finding damage mid-turnover and deciding what to do. Deciding in advance what you will approve without a call — for example, any repair under a set amount — keeps the schedule moving.

Tight gaps and same-week move-ins

When the next tenant moves in within days, work can overlap: repairs and painting in different rooms at once, with more people on site. That costs more per day but can save a vacant week. Decide which matters more for the unit before booking.

Typical turnover schedule

DayWork
Before move-outAccess, COI, elevator, parts, scope
Day 1Move-out photos, clear-out, repairs
Day 2Paint
Day 3Move-in clean
Day 3–4Final check and photo report

Working checklist

  • Keys and access confirmed for day one
  • Building COI and elevator booked
  • Move-out photos taken before work
  • Paint colour and sheen on file
  • Detectors, locks and lights tested
  • Photo report sent to owner

Questions about this guide

How long should a rental turnover take?

About three to four working days for a standard apartment, longer when there is heavy damage or a full repaint.

Can I show the unit during the turnover?

Yes, but showings go better after painting. Schedule them from day three onward.

Should the tenant be at the move-out inspection?

It helps when possible, but dated photos are the key record either way.

What if I find pests during the turnover?

Pause cleaning in that area and bring in a pest control provider; cleaning afterward avoids doing it twice.